Year: 2013
Location: France
Project Duration: 12 months
Capacity: 250 m³/j
Input: SS 1000 mg/l, CDO: 6000 mg/l,
Output: SS 600 mg/l, CDO: 1500 mg/L; Alage reduction more then 95-98%
Year: 2013
Location: France
Project Duration: 12 months
Capacity: 250 m³/j
Input: SS 1000 mg/l, CDO: 6000 mg/l,
Output: SS 600 mg/l, CDO: 1500 mg/L; Alage reduction more then 95-98%
Contact Us